Machine Acceptance in China Before Shipment: FAT Checklist, Test Parts, and Video Report

Machine Acceptance in China Before Shipment: FAT Checklist, Test Parts, and Video Report

Your new machine arrives at the plant. It gets unloaded, installed, connected, and powered up for the first run — and within hours, something is clearly off. The spindle hums louder than it should, the guides move in fits and starts, the tool changer keeps missing, and the first test part falls outside spec.

Article

Introduction

The machine has arrived at your facility. It's been unloaded, installed, connected, and started up for the first time — and within hours, it's clear: something is wrong. The spindle hums louder than it should, the guideways move in fits and starts, the tool changer keeps making errors, and the first test part fails to meet the specified tolerances.

You send a claim to the manufacturer. The response is a standard line: "It worked perfectly at our factory. The problem likely occurred during transport, installation, or operation."

And here's where the real conflict begins.

Without a proper  machine acceptance inspection in China , proving the defect existed before shipment is extremely difficult.

A video from the supplier showing the machine "gliding smoothly along its axes" is not technical evidence.

A photo of the CNC screen turned on is not evidence either.

Even a demo run on an aluminum blank tells you nothing about how the machine will perform with your steel, your cutting parameters, and your tolerances.

Based on technical supervision experience, a significant share of claims against Chinese machines could have been prevented at the FAT stage — Factory Acceptance Test. This is not a formal walkthrough, not a factory tour, and not a friendly meeting with the supplier's manager. FAT for a machine from China is an engineering procedure that verifies geometry, positioning, spindle, CNC, hydraulics, pneumatics, electrical systems, test machining, documentation, and packaging.

The main goal of FAT is not to "find a reason to fight with the factory" but to document the machine's actual condition before packaging and shipment. While the equipment is still at the manufacturer's site, the buyer has leverage: you can demand adjustments, component replacement, re-testing, payment withholding, or refusal to ship. Once the container is sent, that leverage drops sharply.

In this article, we'll cover how a proper pre-shipment machine inspection should be conducted, which tests you can't skip, how to choose a test part, what a video report should include, and which documents you need before signing the acceptance certificate.

What Is FAT and Why You Can't Release Final Payment Without It

Factory Acceptance Test is acceptance testing of equipment at the manufacturer's facility before packaging and shipment. In the context of buying a Chinese machine, FAT ensures the equipment matches the technical specification, contract, and stated parameters.

Simply put, FAT answers four questions:

  1. Is this the exact machine that will be shipped to the buyer?
  2. Does it match the ordered configuration?
  3. Does it hold the stated accuracy?
  4. Can you sign the acceptance certificate and authorize shipment?

Without FAT, the buyer takes on the risk of a pig in a poke. The manufacturer may be reputable, but even good factories have assembly errors, incorrect settings, substituted components, weak packaging, missing documents, or unresolved issues from internal QC.

Why FAT Has Legal Weight

A signed FAT protocol is a document that can serve as the basis for further actions:

  • accept the machine without remarks;
  • accept the machine with a list of required fixes;
  • withhold final payment;
  • demand re-inspection;
  • refuse shipment until defects are resolved;
  • file a claim if a post-delivery issue matches a remark from FAT.

It's important to understand: if FAT wasn't specified in the contract, the supplier may try to reduce the inspection to a simple demonstration. So ideally, the acceptance procedure should be defined in advance: which tests are performed, which instruments are used, who signs the protocol, which parameters are acceptable, and what happens in case of non-conformance.

What FAT Delivers in Practice

A thorough machine acceptance test verifies:

  • geometry of working components;
  • positioning accuracy and repeatability;
  • spindle runout;
  • stability across different speeds;
  • CNC functionality;
  • automatic tool change;
  • hydraulics, pneumatics, and coolant;
  • electrical cabinet, grounding, and safety;
  • actual configuration;
  • documentation and packaging.

For machines priced from 30,000 USD, FAT should already be a mandatory procedure. For CNC machines, heavy machines, gantry centers, boring mills, turn-mill complexes, and equipment for serial production, FAT isn't just desirable — it's critically necessary.

When FAT Is Mandatory

Situation

Is FAT needed?

Why

First order from a new Chinese manufacturer

Yes

No track record on quality or service

Machine costs over 30,000 USD

Yes

The cost of an error is too high

Machine for IT6–IT7 precision

Yes

Accuracy can't be proven without measurements

Custom configuration for your part

Yes

You need to verify your specific configuration

Serial production

Yes

An error will cause mass defects

Simple budget machine for non-critical operations

Recommended

At minimum, verify configuration and startup

FAT Checklist: 10 Essential Items

Below is a baseline CNC machine acceptance checklist that you can adapt for lathes, milling machines, gantry centers, boring mills, and machining centers.

1. Verify Configuration Against Specs Before Powering On

The first thing to do at FAT is not to start the machine but to cross-check it against the contract, specification, and technical requirements. If you start with a demo, you might miss the big picture: the machine may be assembled with a different configuration than what you paid for.

Check:

  • machine model;
  • machine serial number;
  • spindle serial number;
  • CNC model and number;
  • servo motors and drives;
  • guideways;
  • ball screws;
  • tool changer;
  • coolant pump;
  • hydraulic power unit;
  • pneumatic system;
  • electrical cabinet;
  • additional options;
  • tooling package;
  • spare parts kit;
  • documentation.

Pay special attention to nameplates. If the specification lists HIWIN or THK guideways, NSK or SKF bearings, or a Fanuc or Siemens system, this must be confirmed not by the manager's word but by clear photos and videos showing the markings.

What to Capture in Photos and Video

Element

What must be visible

Why

Machine nameplate

Model, serial number, manufacturing date

To rule out machine substitution

CNC

Brand, model, version

Verify spec compliance

Spindle

Marking, power, RPM

Verify ordered configuration

Servo motors

Brand and model

Verify axes and drives

Guideways

Brand markings

Prevent cheap substitutions

Tool changer

Type, number of positions

Verify functionality

Electrical cabinet

Components, markings

Verify electrical and safety systems

If the factory won't let you photograph nameplates or says "that's not necessary," that's a red flag. A reputable manufacturer understands that a pre-shipment machine inspection includes component verification.

2. Geometric Tests

Geometric inspection of a machine from China is one of the key FAT stages. Geometry determines whether the machine will consistently hold dimensions, flatness, perpendicularity, and concentricity.

The inspection must follow a clear methodology, not guesswork. International practice uses ISO 230-1. In Russian and post-Soviet engineering tradition, methods close to GOST 8 and the manufacturer's specifications for a specific machine type may apply.

Check:

  • straightness of travel along X, Y, Z axes;
  • perpendicularity of axes;
  • parallelism of table travel;
  • spindle concentricity;
  • spindle runout;
  • table flatness;
  • guideway parallelism;
  • relative positioning of working components.

Minimum Instrument Set

Check

Instrument

Comment

Straightness of travel

Dial indicator, straightedge, laser

Indicator gives a baseline; laser gives precision

Perpendicularity of axes

Granite square, indicator

Check at multiple points

Spindle runout

Indicator, 0.001 mm

Must be captured on video

Table flatness

Straightedge, indicator

Especially important for milling centers

Positioning

Laser interferometer

Mandatory for IT6–IT7

Reference Control Parameters

Component / Parameter

Good level

Acceptable for a standard machine

Risk

Spindle runout

up to 0.003 mm

up to 0.005 mm

Above 0.005 mm — risk of defects

Positioning repeatability

±0.003–0.005 mm

±0.008–0.01 mm

Higher — problem for precision parts

Perpendicularity of axes

up to 0.01 mm / 300 mm

up to 0.02 mm / 300 mm

Can cause form errors

Shop temperature

20±2°C

18–24°C with recording

Without temperature data, numbers are disputable

Spindle heating

up to 40°C after 2 hours

up to 45°C

Higher — check bearings

Important: you can't assess geometry in a cold shop in winter or a hot shop in summer without recording temperature. Metal expands, and measurement results may be inaccurate. If the temperature deviates from normal, it must be noted in the protocol.

3. Positioning and Repeatability Testing

Machine positioning repeatability testing is a separate FAT block that can't be replaced by "running a program." Just because the machine moves smoothly along its axes doesn't mean it returns to the exact same point accurately.

A proper check requires a laser interferometer. An indicator can help with basic diagnostics, but it doesn't replace measurement along the full axis length.

How the Test Is Conducted

For each axis, a series of movements is performed:

  • at least 10 cycles;
  • at different points in the work envelope;
  • with deviation recording;
  • with graph plotting;
  • with temperature noted;
  • with feed rate noted;
  • signed by the responsible person.

Bad practice: testing only the center of the work envelope. On many machines, it's the edges of the machining zone that reveal real problems: geometry drop-off, backlash, ball screw error, thermal expansion, or insufficient compensation.

What the Protocol Must Include

Parameter

Must be specified

Axis

X / Y / Z / A / B / C

Travel length

In millimeters

Number of cycles

At least 10

Maximum deviation

In mm or microns

Repeatability

Separately for each axis

Temperature

In the shop and at the machine

Instrument

Model and serial number

Operator

Factory engineer / inspector / buyer's representative

If the supplier says "you don't need an interferometer," look at the machine class and part requirements. For rough machining, a basic check may suffice. But for precision housing parts, fits, molds, hydraulic components, aerospace or energy components — FAT without an interferometer will be incomplete.

Advertisement

TOP 5 GLOBAL TONER MANUFACTURERS — YOUR PREMIUM COLOR PRINTING EXPERT

Flawless Colors. · Guaranteed Performance. · With UNICO, your seal speaks for quality.

Learn more

4. Test Machining: A Control Part Instead of a Demo

Test parts for a CNC machine are the most honest way to verify how the equipment performs in real work. But only on one condition: the part must be yours or as close as possible to your production tasks.

The factory often offers to machine its own demo part. Usually it's chosen so the machine looks good: soft material, convenient geometry, gentle parameters, simple dimensions, no critical fits.

That's not FAT. That's a presentation.

What Part You Need

The test part should include:

  • face milling;
  • contour milling;
  • drilling;
  • boring;
  • threading;
  • pockets;
  • internal and external corners;
  • surfaces with roughness requirements;
  • holes with tight tolerances;
  • features that test concentricity and perpendicularity.

The material must be real. If you'll be machining 1045 steel, stainless steel, cast iron, or heat-resistant alloy, you can't accept the machine based on an aluminum blank. Aluminum produces a pretty picture but won't reveal the machine's rigidity, spindle stability, or behavior under load.

Example Test Part for a Milling Center

Part feature

What it tests

Plate 150×150×50 mm

Flatness and milling stability

Holes Ø10, Ø15, Ø20, Ø30

Drilling, boring, concentricity

Hole Ø20H7

Ability to hold tight tolerance

Contour milling

Interpolation and path accuracy

Internal pocket

Rigidity and vibration

Thread M10

Threading cycle performance

Surface Ra 3.2

Roughness

Perpendicular walls

Geometry and axis accuracy

How to Measure the Part

Calipers are only good for rough checks. For a real FAT, you need:

  • micrometer;
  • bore gauge;
  • dial indicator;
  • surface profilometer;
  • coordinate measuring machine (CMM);
  • measurement report for each critical dimension.

Control machining on a CNC machine must be captured on video: blank loading, clamping, program start, machining, part removal, measurement. If the supplier only shows a finished part on the table — that's not proof.

5. Spindle Inspection

The spindle is one of the most expensive and critical components. An error here can lead to vibration, poor surface finish, accelerated tool wear, part defects, and costly repairs.

What to Check

  1. Spindle runout
    Check with a high-precision indicator. For most machining centers, a good target is up to 0.005 mm. For higher-precision work, requirements may be tighter.
  2. Heating
    The spindle must run at various speeds for at least 1–2 hours, not just a few minutes. Housing temperature is recorded with a thermocouple or thermal imager. If the housing noticeably overheats within a short time, that's a risk of bearing, lubrication, or assembly issues.
  3. Noise
    A sound level meter isn't just a formality. Uneven sound, humming, howling, or metallic overtones may indicate bearing or balancing problems.
  4. Vibration
    At high speeds, the machine shouldn't "sing," shake, or transmit vibration to the frame.
  5. Acceleration and deceleration
    Test all stated speed ranges: low, medium, maximum.
  6. Automatic tool change
    If the machine has an ATC, run a series of tool changes. Not one or two — at least 20–30 cycles. Check time, grip accuracy, absence of impacts, and sensor correctness.

Spindle Inspection Table

Parameter

How to check

Normal result

Red flag

Runout

Indicator, 0.001 mm

up to 0.005 mm

Fluctuating or high runout

Heating

1–2 hours of operation

up to 40–45°C

Rapid overheating

Noise

Sound level meter

up to 75 dB in typical mode

Humming, howling, metallic sound

Speed

All ranges

Smooth acceleration

Jerking, vibration

ATC

20–30 changes

No errors

Grip errors, impacts

6. CNC System Inspection

The CNC system is the machine's brain. Even if the mechanics are well-assembled, poor CNC setup can create problems in real operation.

Check:

  • brand and model match the specification;
  • interface language;
  • parameter accessibility;
  • axis correctness;
  • manual mode operation;
  • automatic mode operation;
  • loading your control program;
  • drilling, boring, and threading cycles;
  • tool compensation;
  • interpolation;
  • alarm messages;
  • parameter backup.

You can't accept a machine based only on the manufacturer's demo program. At FAT, you need to load your program or specially prepared test code. If the machine must work with a specific CAM system, verify post-processor compatibility.

What You Must Take With You

  • CNC parameter backup;
  • alarm code list;
  • parameter recovery instructions;
  • electrical diagram;
  • servo drive data;
  • password or access procedure for service settings, if provided in the contract.

If CNC parameters aren't saved, recovery after a failure, battery replacement, or operator error can take weeks.

7. Hydraulics, Pneumatics, and Coolant Inspection

Hydraulics and pneumatics rarely look impressive on video, but they're often the cause of problems after startup.

Check:

  • system pressure;
  • pressure stability;
  • absence of leaks;
  • pump operation;
  • hose condition;
  • fitting quality;
  • cylinder operation;
  • chuck clamp/unclamp;
  • air blow-off operation;
  • coolant supply system;
  • filtration;
  • presence of magnetic inserts and filters.

Pay special attention to connection points. Oil seepage, weak fittings, sloppy hose routing, and missing labels are signs of poor assembly culture.

Minimum Check

System

What to check

How to record

Hydraulics

Pressure, leaks, pump

Video + photo of pressure gauge

Pneumatics

Pressure, clamps, valves

Video of operating cycle

Coolant

Supply, filtration, pump

Video of coolant delivery to tool

Hoses

Labeling, routing, protection

Close-up photos

Fittings

Seepage, tightness

Photos after 30–60 minutes of operation

8. Electrical and Safety Inspection

The electrical cabinet is a place you absolutely must look inside. A nice exterior doesn't guarantee clean electrical assembly.

Check:

  • diagram matches actual wiring;
  • wire labeling;
  • terminal quality;
  • grounding;
  • fan operation;
  • cabinet air conditioner, if equipped;
  • emergency stop;
  • limit switches;
  • door interlocks;
  • indicator lights;
  • safety sensors;
  • overload protection.

Ground resistance should be tested with an instrument. Target: no more than 4 ohms unless otherwise specified by site requirements and local codes.

You must test the emergency stop button. Not visually — actually: the machine must stop dangerous motion, the system must produce a correct signal, and restart must only be possible after a proper alarm reset.

9. Packaging and Marking Inspection

Many buyers mistakenly think FAT ends after the test part is machined. No. Until the machine is properly packed, the risk remains.

Bad packaging can destroy a good machine.

Check:

  • wooden crate or metal frame;
  • moisture barrier film;
  • silica gel;
  • anti-corrosion treatment;
  • securing of moving components;
  • machine fastening to the base;
  • guideway protection;
  • electrical cabinet protection;
  • center of gravity marking;
  • "do not tip," "fragile," "keep dry" signs;
  • packing list;
  • photos before closing the crate;
  • photos after closing the crate.

For heavy machines, gantry centers, and long equipment, packaging must be discussed in advance. If the machine ships by sea, moisture protection is critical. If the shipment is oversized, verify the fastening and loading plan in advance.

10. Documentation Inspection

Documents aren't a secondary item. Without them, you can face problems during installation, operation, service, customs, and warranty disputes.

Required Documents

Document

Why it's needed

Geometric test protocol

Confirms geometry before shipment

Positioning accuracy protocol

Records axis accuracy

Control machining protocol

Confirms results on the test part

FAT Acceptance Certificate

The main acceptance document

Packing List

Needed for logistics and customs

Electrical diagram

Needed for maintenance and repair

Hydraulic / pneumatic diagram

Needed for diagnostics

Operation manual

Needed by the operator and repair service

Component certificates

Confirm the configuration

FAT photo and video archive

Evidence base

If the manual in English isn't ready yet, at least get the English version before shipment. Translation can be refined later, but electrical diagrams, hydraulic schematics, CNC parameters, and the FAT protocol must be in the buyer's hands before the machine ships.

Test Part: How to Choose and What to Check

test part for a milling center or lathe should be diagnostic, not pretty. Its job is to expose the machine's weak points.

Selection Criteria

The part should:

  • replicate your actual production task;
  • include critical operations;
  • contain dimensions with tolerances;
  • test geometry;
  • test machining stability;
  • be made from your material;
  • be measured with proper instruments.

If you're buying a machine for housing parts, the test part should include surfaces, holes, pockets, boring, threads, and datum features. If it's a lathe — external turning, internal boring, grooves, threads, facing, runout and concentricity checks.

What to Measure

Control group

What is measured

Instrument

Dimensions

Diameters, depths, distances

Micrometer, bore gauge, CMM

Geometry

Perpendicularity, parallelism, concentricity

CMM, indicator

Roughness

Ra 1.6 / 3.2 / 6.3

Profilometer

Repeatability

Multiple identical features

Measurement series

Threads

Go/no-go

Gauges

Surface

Vibration marks, waviness

Visual + profilometer

The Biggest Mistake

The biggest mistake is accepting a machine based on one part made under ideal conditions, at the manufacturer's parameters, from convenient material, and measured with calipers.

Proper FAT requires: your part, your material, your parameters, your measurement, your protocol.

Video Report: Can You Trust Remote Acceptance?

FAQ: Machine Acceptance in China Before Shipment: FAT Checklist, Test Parts, and Video Report — China Global Hub